Contractor Final Bill and No-Claim Letter

एक नज़र में

कीमत
मुफ़्त
स्टाम्प ड्यूटी
A receipt for payment of Rs 5,000 or more must bear a revenue stamp of Re 1 under Article 53, Schedule I of the Indian Stamp Act, 1899, affixed and signed across by the Contractor on receiving the final payment in cash or by an instrument other than by way of a bank transfer that already carries its own proof of payment — banks and counters may still ask for it out of habit even for a bank transfer; confirm current practice with the stamp vendor or bank if in doubt.
रजिस्ट्री
Not registrable — it settles an account and creates no interest in immovable property.
गवाह
Not legally required.

मुफ़्त

दस्तावेज़ मुफ़्त हैं। केवल किट के पैसे लगते हैं।

आसान सवाल, पूरा ड्राफ़्ट स्क्रीन पर, Word में डाउनलोड करें।

सभी कीमतें देखें

इन नामों से भी

  • final bill and no dues certificate
  • full and final settlement letter construction
  • no claim certificate contractor
  • thekedar da final bill
  • ਠੇਕੇਦਾਰ ਦਾ ਅੰਤਿਮ ਬਿੱਲ
  • contractor no dues letter
  • final settlement construction contract

दस्तावेज़ ख़ुद अंग्रेज़ी में है। भारत में इस तरह के काग़ज़ आमतौर पर अंग्रेज़ी में ही बनते हैं, और रजिस्ट्रार, बैंक या अदालत में वही शब्द पढ़े जाते हैं जो लिखे गए हैं। जिन दस्तावेज़ों के हिन्दी अनुवाद को हम जाँचकर स्वीकृत कर देते हैं, उनके लिए यह मंच अंग्रेज़ी के साथ वह अनुवाद भी देता है; अनुवाद और अंग्रेज़ी पाठ में अंतर होने पर अंग्रेज़ी पाठ ही मान्य होगा।

कब ज़रूरत पड़ती है

A construction, labour or interior job is finished and the last payment is being made. This records the final bill — original contract value, any extra/variation work, amount already paid, and the closing balance — and, once that balance is paid, the contractor's written confirmation that it has no further claim against the owner for that job.

और पढ़ें

Use this alongside the Defect Notice to Contractor if a defect is later found — signing this letter does not itself waive the defect-liability period already promised in the construction contract, unless you say so expressly below.

क्या यह यहीं भरा जा सकता है

यह यहीं भरा जा सकता है

यह दस्तावेज़ आप इसी साइट पर भर सकते हैं, और कुछ भी तय करने से पहले पूरा मसौदा स्क्रीन पर पढ़ सकते हैं। यह ध्यान से तैयार किया गया प्रारूप है; आपके अपने हालात पर दी गई सलाह नहीं।

इसे भरना शुरू कीजिए
स्टाम्प ड्यूटी, रजिस्ट्री और गवाह देखें

नीचे जो लिखा है वह पंजाब और चंडीगढ़ के लिए है। इसमें वहीं की स्थिति दी गई है, यह नहीं कि यह कहाँ-कहाँ कैसे बदलती है — यानी नीचे की रकमें वही हैं जो लागू होती हैं। दरें बदलती रहती हैं, इसलिए सब-रजिस्ट्रार दफ़्तर से पक्का कर लेना ठीक रहता है। अगर प्रॉपर्टी भारत में कहीं और है, तो इनमें से कुछ भी आपके लिए नहीं है।

स्टाम्प ड्यूटी

A receipt for payment of Rs 5,000 or more must bear a revenue stamp of Re 1 under Article 53, Schedule I of the Indian Stamp Act, 1899, affixed and signed across by the Contractor on receiving the final payment in cash or by an instrument other than by way of a bank transfer that already carries its own proof of payment — banks and counters may still ask for it out of habit even for a bank transfer; confirm current practice with the stamp vendor or bank if in doubt. Beyond that, this letter is not otherwise chargeable as a separate instrument.

रजिस्ट्री

Not registrable — it settles an account and creates no interest in immovable property.

नोटरी

Not legally required.

गवाह

Not legally required.

स्टाम्प पेपर का अनुरोध करें

Sample preview — placeholder answers, not your data

FINAL BILL AND NO-CLAIM LETTER

Date: 1 April 2026
Place: Mohali

Project: House construction at Plot No. 118, Sector 70, Mohali, under contract dated 4 January 2026

FINAL ACCOUNT
ParticularAmount
Original contract value₹32,00,000 (Rupees Thirty Two Lakh only)
Extra/variation work (Additional boundary wall and a store room not in the original scope)₹1,80,000 (Rupees One Lakh Eighty Thousand only)
Total amount billed₹33,20,000 (Rupees Thirty Three Lakh Twenty Thousand only)
Already paid before this final payment₹31,20,000 (Rupees Thirty One Lakh Twenty Thousand only)
Final payment now made₹2,00,000 (Rupees Two Lakh only)

Mode of final payment: NEFT transfer to the Contractor’s bank account

NO-CLAIM DECLARATION

I/We, Balwinder Singh, Sai Construction Co., of SCO 44, Phase 3B2, Mohali, having carried out the work referred to above for Ramandeep Singh, of House No. 214, Sector 70, Mohali, hereby acknowledge receipt of the final payment of ₹2,00,000 (Rupees Two Lakh only) stated above, in full and final settlement of all amounts due to me/us for the work.

I/We confirm that, on receipt of this final payment, I/we have no further claim, demand or dispute of any kind against the Owner in connection with the work referred to above, whether for the contract price, extra or variation work, retention, interest or otherwise.

The defect liability period already agreed in the construction contract continues to apply and is not affected by this letter

Received with thanks.

CONTRACTOR

_________________
Balwinder Singh, Sai Construction Co.

Acknowledged by the Owner:

OWNER

_________________
Ramandeep Singh