Variation Order No. 1
This Variation Order is made at Mohali on 2 April 2026
BETWEEN
Anmol Kaur, resident of Flat No. 604, Sector 82, Mohali ("the Owner");
AND
Décor Craft Interiors, of SCO 212, Sector 34-A, Chandigarh ("the Contractor").
1.1 The Parties are bound by House Construction Contract dated 4 January 2026 ("the Contract") for work at Plot No. 118, Sector 70, Mohali. This Variation Order varies the Contract as stated below and is to be read with it.
2.1 Kind of change: Additional work.
2.2 The change is as follows: Additional boundary wall, 60 running feet, 6 ft high, in brick masonry with plaster on both faces; store room 8 ft x 10 ft in the rear corner.
2.3 Reason for the change: Requested by the Owner after the original contract was signed
2.4 The Contractor shall not begin the changed or additional work, and the Owner shall not be liable to pay for it, until this Variation Order has been signed by both Parties. Work omitted under this Order shall not be carried out.
3.1 Effect of the change on the contract value: the change adds to the contract value.
3.2 The amount of the change is ₹1,80,000 (Rupees One Lakh Eighty Thousand only), exclusive of goods and services tax and any other tax or cess payable in addition, unless stated otherwise.
3.3 The amount was worked out as follows: At the item rates of the original contract; for items not in it, at rates agreed in writing before the work starts.
3.4 The contract value was ₹32,00,000 (Rupees Thirty Two Lakh only) and is now ₹33,80,000 (Rupees Thirty Three Lakh Eighty Thousand only).
3.5 Payment for the varied work: Billed in the running bills as the varied work is measured; retention applies as in the original contract
4.1 The completion date under the Contract was 1 April 2026.
4.2 The completion date is extended to 2 April 2026. Reason: Extra work needs about five weeks beyond the original timeline
4.3 Any delay penalty or liquidated damages under the original contract will apply from the new completion date, not the earlier one.
5.1 Except as changed by this Variation Order, the Contract continues in full force, including its terms on retention, defect liability, insurance, safety and dispute resolution, which apply to the varied work as they apply to the rest.
5.2 No other change in the work, price or time is agreed unless it is recorded in writing and signed by both Parties.
IN WITNESS WHEREOF the Parties have signed this Variation Order at Mohali on 2 April 2026.
OWNER
_________________
Anmol Kaur
CONTRACTOR
_________________
Décor Craft Interiors
WITNESSES