Bill: Running Bill No. 3
Date: 2 April 2026
Place: Mohali
Project: House construction at Plot No. 118, Sector 70, Mohali, under contract dated 4 January 2026
Stage of work covered: Ground-floor roof slab and brickwork up to first-floor level
Contractor: Balwinder Singh, Sai Construction Co., of SCO 44, Phase 3B2, Mohali
Owner: Ramandeep Singh, of House No. 214, Sector 70, Mohali
The work below was measured at the Site on 1 April 2026, jointly by Balwinder Singh (Contractor) and Ramandeep Singh with Er. Sandeep Kumar (Owner’s engineer).
- 1. RCC roof slab, 1,120 sq ft x 5 in, 56 cu ft @ Rs 380 = Rs 21,280
- 2. Brickwork in superstructure, 640 cu ft @ Rs 210 = Rs 1,34,400
- 3. Plaster, internal, 2,800 sq ft @ Rs 28 = Rs 78,400
| Particular | Amount |
|---|---|
| Contract value | ₹32,00,000 (Rupees Thirty Two Lakh only) |
| Value of all work measured to date | ₹18,40,000 (Rupees Eighteen Lakh Forty Thousand only) |
| Less: value billed in earlier bills | ₹12,00,000 (Rupees Twelve Lakh only) |
| Value of work in this bill | ₹6,40,000 (Rupees Six Lakh Forty Thousand only) |
| Less: retention (5%) | ₹32,000 (Rupees Thirty Two Thousand only) |
| Less: advance adjusted | ₹60,000 (Rupees Sixty Thousand only) |
| Less: other deductions (Cost of cement issued by the Owner beyond the agreed quantity) | ₹8,500 (Rupees Eight Thousand Five Hundred only) |
| Add: GST, as per the Contractor's tax invoice | ₹25,000 (Rupees Twenty Five Thousand only) |
| Less: tax deducted at source | ₹25,000 (Rupees Twenty Five Thousand only) |
| Net amount payable now | ₹5,39,500 (Rupees Five Lakh Thirty Nine Thousand Five Hundred only) |
I/We, Balwinder Singh, Sai Construction Co., state that the quantities above are those measured at the Site and that the rates are those agreed in the contract. This bill is for the stage described above only; it is not a final bill and does not close the account.
CONTRACTOR
_________________
Balwinder Singh, Sai Construction Co.
The Owner has checked the measurements jointly with the Contractor and certifies this bill for payment
Remarks: Plaster in the rear bedroom to be redone before the next bill; Rs 4,000 held until then
Payment of the net amount above is without prejudice to the Owner's right to have any defect in the work corrected under the contract, and to the final measurement and final account.
OWNER
_________________
Ramandeep Singh