ANNUAL MAINTENANCE CONTRACT
This Contract is made on 1 April 2026 at Panchkula between:
(1) Green Park Residents Welfare Association, Sector 21, Panchkula, acting through Harjinder Singh, President (the "Society"); and
(2) Kone Elevators Service, Industrial Area Phase 2, Mohali, GSTIN X (the "Contractor").
- 1. What is covered. From 2 April 2026 for 12 months the Contractor shall maintain, service and repair the Society's lift(s), on a comprehensive basis. The equipment is: Three passenger lifts at Tower A, make Kone, 8-person capacity, serving ground to 12th floor.
- 2. Scheduled service. The Contractor shall visit 2 time(s) a month to inspect, clean, lubricate, adjust and test the equipment, and shall keep a service register at the site in which each visit is entered and signed by the Society's representative.
- 3. Breakdowns. On a call from the Society the Contractor shall attend within 4 hours and shall repair the fault as soon as it reasonably can, telling the Society the cause and what it has done. If a person is trapped in a lift, the Contractor shall treat the call as an emergency and attend at once.
- 4. Parts. In a comprehensive contract the Contractor supplies the labour, the lubricants and consumables and the spare parts needed to keep the equipment running, other than parts damaged by misuse, vandalism, flood, fire or a fault in the power supply, which the Society shall pay for.
- 5. Fee and payment. The Society shall pay the Contractor Rs 96,000 for the year, inclusive of GST, in four equal quarterly instalments, each paid in advance, against a bill.
- 6. Safety, licences and staff. The Contractor shall use only trained and competent persons, and shall follow the safety rules for this kind of equipment. The Society remains responsible for holding any licence, inspection certificate or consent that the law requires for the equipment itself, and the Contractor shall give the help and records needed for any inspection. The Contractor shall pay its staff and meet its duties as their employer.
- 7. Damage and liability. The Contractor shall make good any loss or damage to the Society, its residents or their property, or injury to any person, that results from the Contractor's negligence or from work done outside this Contract's terms.
- 8. Ending the Contract. Either side may end this Contract by giving the other 30 days' written notice. The Society may end it at once by written notice if the Contractor repeatedly fails to attend breakdowns or to do the scheduled service. The Society shall pay for the service done up to the end, in proportion to the fee.
- 9. Disputes. The parties shall first try to settle any dispute by talking. If that fails, the courts at Panchkula shall have jurisdiction.